Translate

2023年9月28日星期四

How to Reassemble a Stroke Motor Speed Reducer

   How to Reassemble Doosan DX520LC and DX480LC Hydraulic Excavator Stroke Motor Speed Reducer

Doosan Diagnostic Tool UVIM Support Doosan Excavators High Quality 

1.      Install seal to jig. Figure 92.

  

   

2.      Install jig to housing. Figure 93.

 

 

3.      Clean seal surface. Figure 94.

 

 


    2020 Doosan Daewoo Excavator Operation and Repair Manual PDF

4.      Install seal to hub using jig used in Step 1. Figure 95.

 

       

5.     Apply lubricant to seal surface. Figure 96.

 

 


 

6.      Support ball bearing housing with spacers (1 and 2, Figure 97) and install bearing into housing. Install spacer between balls,noting diameter shown in illustration.

 


  2022.11 Doosan DMS-5 3.0.5 Data Monitoring System Diagnostic Software

7.      Install upper balls and upper housing. Figure 98.


   8.      Itall hub to housing. Figure 99.

 

 


   

9.      Press hub into housing using a press and a stopper. Figure 100.

 


    Doosan Diagnostic Tool DDT G2 SCAN( ECU ,DCU)Software 2016

10.    Install four bushings using a press. Figure 101.

 

 


        

11.   Assemble planetary gear assembly. Figure 102.


 12.    Install four planetary gear assemblies, using press. Figure 103.

 


       

13.   Tighten gear box of planetary gear assembly to 150 Nm (110.7 ft lb). Figure 104.

 

 


        

14.   Assemble third shift sun gear. Figure 105.

 


          15.   Assemble  the  second  shift   reduction  assembly.  Figure 106.


 16.    Place planetary gear carrier on hub. Figure 107.

 

 


    

17.    Press planetary gear carrier into hub. Figure 108.

 


 

Doosan Diagnostic Tool UVIM Support Doosan Excavators High Quality

  18.   Apply loctite to planetary gear carrier fastening bolts. 19.    Install and tighten bolts. Figure 109.

NOTE:      In  next step,  the  O-ring and backup rings are

different. Be careful not to switch them.

 

 


 

20.    Install O-ring to end cover. Figure 110.

 


 21.    Install end cover to housing.

NOTE:      Apply Loctite 243 to bolts and torque to  10 Nm

(7.38 ft lb). Figure 111

 

 

 

    22.   Tighten plugs to 6 - 8 Nm (4.42 - 5.90 ft lb). Figure 112.

 


          

23.   Turn housing over and install second shift sun gear. Figure 113.

 


  

24.    Install first shift planetary gear assembly. Figure 114.


 

  25 Install first shift sun gear. Figure 115


 

26.    Install O-ring (1, Figure 116) and backup ring (2) into hub groove.

NOTE:      The  O-ring  and backup  rings are different. Be

careful not to switch them.


 

27  Install   brake   shaft   while   turning   the   reduction   gear assembly. Figure 117.



       

 28.    Install  brake  disc  assembly,  starting  with  a  copper  disc (seven pieces) and alternating with steel discs (six pieces). Figure 118 and Figure 119.


 

 

29.    Install jig to hub and insert spring retainer disc under left side of retaining ring. Figure 120.

 


     Heavy Duty Truck Diagnostic Tool

30.    Install retaining ring using retaining ring pliers. Figure 121.



31.    Install O-ring to hub groove. Figure 122.

 

 


 

32.    Place brake piston inside hub being careful not to damage seal. Figure 123.

 


       

33.    Insert springs into brake piston holes. Figure 124.

 


 

 

34.    Install retainer disc. Figure 125.


35.    Install O-ring to motor flange groove. Figure 126.

 

 


      

36.   Tighten motor flange to hub. Figure 127.

 



How to relieve hydraulic pressure in the hydraulic circuit of a CAT excavator.

  How to relieve hydraulic pressure in the hydraulic circuit of 312D2 and 313D2 excavators   Steps to relieve pressure:   Caterpillar ET 202...